Onshore wind turbines fall within the scope of facilities classified for environmental protection (ICPE).
The operation of a wind farm with one or more wind turbines shall be subject to:
* Authorisation where the installation includes at least one wind turbine with a height of more than 50 metres or where the installation includes only wind turbines with a mast between 12 and 50 metres and with an installed capacity exceeding 20 MW.
* Declaration where the installation includes only wind turbines with a height of between 12 and 50 metres and with an installed capacity of less than 20 MW.
Two ministerial orders on general requirements, as well as a decree and ministerial order specific to financial guarantees dated 23 and 26 August 2011, regulate the operation of these facilities.
Legend:
Blue: In operation (built and connected to the network)
Green: Authorised (licensed but not built or connected to the network)
Yellow: In the course of investigation
Red: Refused (rejection, refusal or divestment)
Build on reliable and scalable technology
FAQ
Frequently Asked Questions
Some basic informations about API Store ®.
Operation and development of APIs are currently fully funded by company Apitalks and its usage is for free.
Yes, you can.
All important information such as time of last update, license and other information are in response of each API call.
In case of major update that would not be compatible with previous version of API, we keep for 30 days both versions so you will have enough time to transfer to new version. We will inform you about the changes in advance by e-mail.