The Construction Status Q3 2020 report shows that 9,562 homes were under construction at end Q3 2020; and some 3,133 homes had been approved and were about to go on site. The full programme listed in the report now includes 2,283 schemes (or Phases), delivering 31,862 homes — a substantial increase on the 22,721 homes which were in the programme at the end of Q3 2019